Design/Engineering of three streets - A contact was awarded for $40,100 to Beckett and Raedar, of Ann Arbor, to design and perform construction management on two streets: High Street (W. Main to W. Dunlap), improve asphalt road, curb and sidewalks; and Elmsmere (E. Chigwidden to Coldspring), improve concrete road and sidewalks; and design work only of E. Cady, enabling proposed new building construction on the south side of Cady to precede road replacement. The E. Cady design document will facilitate bids and allow DPW to establish the grade, which affects drainage.

Earlier start for City Council meeting – The Council voted to begin the meetings at 7 p.m., rather than 7:30 p.m., starting with the Jan. 17 meeting.

 

 