Grading will begin on The Downs the week of May 20

BNV Earthmovers, of Brighton, has been issued a grading permit for the Phase I north, which includes the area north of the Beal Street extension and west of Griswold. This encompasses the future Central Park as well as the Beal Street extension that starts at S. Center Street and continues to Griswold St. The site will be brought to rough elevations and leveled in accordance with the grading plan.

The city has two inspectors visiting The Downs site at least daily: the city’s building official and an OHM engineering inspector. They monitor dust control activities, inspect soil erosion and sedimentation control measures, and observe other on-site construction activities. The purpose of dust control measures is to reduce the potential for construction activities to generate dust and to limit the dust that travels off the construction site. Dust control measures being implemented include wind barriers surrounding the property, regular water applications, and maintaining existing vegetative cover as long as possible. The city’s inspectors report that overall, the dust control measures are being administered properly and functioning as intended.

Air monitoring is continuing around the site and pest control measures remain in place at the buildings still standing. The air monitoring consultant, Atlas, is monitoring for lead, cadmium and asbestos, all of which have been below detectable levels. Pest activity has been minimal and is noted primarily at the bait stations. Soil erosion control measures are also in place and are being monitored by Franklin Construction Co. and OHM on the city’s behalf.

Any observations or concerns about the project activities can be directed to [email protected] [email protected]

Presentation made at Special meeting of City Council on April 24
Downs update by Seth Herkowitz, of Hunter Pasteur – Permits for the Riverpark have been submitted to EGLE and FEMA and the public comment period expired on April 15. He expressed gratitude for the $1 million EGLE grant secured through the Brownfield Redevelopment Authority. Environmental testing will begin in early May. Bi-weekly meetings between the developer and city staff are going well and will improve the project, going forward. Consultant ECT has approved 18 of 19 structures for abatement; the last remaining one is the grandstands, which will be demolished by the end of June. Three buildings in the south portion have been torn down this week. DTE has delivered light poles to the construction site. Air quality reports will be submitted to the city as they are received by the developer. Toll Brothers is commencing the first phase of the project west of Center. Two vacant structures were demolished and grading will begin after permits are obtained.

View meeting video here for Herkowitz's full presentation. 

Downs Redevelopment Public Meeting - held March 26, 2024
Strong attendance at Downs demolition/redevelopment meeting

The city hosted a meeting at the Northville Community Center on March 26 that drew approximately 140 people to learn about the demolition and construction plans for the Downs redevelopment project.

City Manager George Lahanas opened the meeting by welcoming citizens. “I’m really excited about this project,” he said. “It’s bringing a lot of great things to the community,” Topping the list are a daylighted river, new trails and a “smart, sustainable development” that “repurposes land without the need to build additional infrastructure.”

He noted the city has a lot in alignment with the developer, Hunter Pasteur, and its partners, but also has the responsibility of ensuring the project is properly implemented. He introduced the city team working on the development oversight who were present at the meeting, including DPW Director Mike Domine, Strategic Planning Director Wendy Wilmers Longpre and OHM engineer George Tsakoff.

Hunter Pasteur Executive Seth Herkowitz introduced his team: Hunter Pasteur VP of Development Omar Eid; Andy Milia and Ian Sakwa, of Franklin Construction; and Tim O’Brien, a project partner.

Project Manager Sakwa presented information about the status of the project site work.

The project is beginning with a 6-foot-tall fence and wind screen being installed around the redevelopment site, with a secure gate at the entrance on Center Street and “no trespassing” signs. City officials who need to inspect the site will be accompanied by the developer or a partner representative, Herkowitz said.

The demolition company, Renascent, will remove 19 buildings on the site and a small building on the track, along with the asphalt and concrete. These materials will be loaded into trucks and crushed off site. Water will be sprayed on the debris to help contain dust. Griffin Pest Solutions has been contracted to handle the pest control and has found small animals such as raccoons and porcupines on the site as well as mice but very few rats. Pest control will involve fumigating any underground tunnels and baiting with poison. Vermin are expected to remain within the confines of the screened fence during this process.

Midwest Environmental is the asbestos abatement contractor, charged with removing any asbestos identified in the asbestos survey. Before the buildings are demolished a third-party consultant, hired by the developer, will perform clearance testing to confirm all asbestos is removed and also conduct air quality monitoring. Water will be used on the debris to help prevent particles from becoming airborne.

A joint permit application is in process with EGLE and FEMA for the river daylighting. The new river bed will be graded and stabilized and then the culvert will be broken first at the south end then at the north end, allowing the encased river to flow into the new channel. Soil erosion permits are being obtained through Wayne County and inspections of the soil erosion control will be conducted by Franklin Construction.

The sidewalks on River, Center and Cady will remain open during demolition and construction.

Hours of operation will abide by city code, which is seven days a week, from 7 a.m. to 6 p.m. At this stage, the developer doesn’t anticipate weekend work except for the occasional Saturday.

Both the city manager and developer said they want to keep information open and available to the public throughout the redevelopment process. Hunter Pasteur will maintain The Downs website, Northvilledowns.info, for the duration of the project and will regularly post project documents and updates. HP has also established an email for citizen comments and observations.

At the end of the meeting, the developer and city answered questions from the public.

The developer plans to have a pre-construction meeting with the city soon and will also attend public sessions held by the city to provide construction updates to the public.

Lahanas encouraged individuals to sign up for email notifications about the Downs demolition and construction, which will be delivered monthly or more frequently as the project gets underway. (See link below.) Articles will also appear in City News and on the city website, where a new landing page is being devoted to this project.

The Audio recording of the meeting held at the Northville Community Center.

View the presentation given by Hunter Pasteur at the meeting. 
View Final Site Plan
All renderings and submissions reviewed by the Planning Commission and Historic District Commission relating to the Downs project reside on the Proposed Redevelopment Projects page. For convenience, here's the link to the approved final site plan.
You’re invited to join the “Downs Reconstruction Update” email list
The city administration is inviting anyone interested in the Downs redevelopment project to join the city-generated email list to let them know what’s happening on the construction site. Members of the city’s team* will meet with the developer’s team bi-monthly to review action plans, discuss concerns and resolve any problems as the project moves forward. We anticipate sending out monthly emails and will increase the frequency when there’s new information to share. If you’d like to be added to the list, please sign up here.

Please note that you can still receive news about the Downs redevelopment project in City News and Northville Matters, but the email notifications will be more specific about what’s happening on site in terms of dust, pest control, sanitation, traffic, etc.

*The city’s team working on the Downs project:
City Manager George Lahanas
Director of Strategic Planning and Special Projects Wendy Wilmers-Longpre
DPW Director Mike Domine
OHM Engineer George Tsakoff
City Building Official/Project manager
Finance Director Sandi Wiktorowski
Communications Manager Liz Cezat
Director of Community Development